After previously suggesting that it would propose a "new route" from Groveton to Canada for the proposed high-voltage tower and transmission line project, Northern Pass recently indicated that such announcement would not be forthcoming before fall of 2011. Read Chris Jensen's story on NHPR here.
Equally unresolved is what PSNH and Northern Pass might propose to overcome the growing opposition to the proposed project from 33 communities along 140 miles of existing PSNH right-of-way, where the project would require additional towers of greater height and expansion of the existing ROW. Northern Pass has said that they need to expand nearly 19 miles of that existing ROW, and that on average the towers will be highest between Franklin and Deerfield.