HB 569 is a good first step toward recognizing that there are new burial technologies that can mitigate the adverse impacts of large new overhead transmission facilities. It also makes a clear statement that New Hampshire should join with our neighboring states to encourage the use of these new technologies to protect our natural landscapes from degradation.
You can read an op-ed written by Sugar Hill resident Nancy Martland,
HB569: Buried Lines Should Be the Preferred Option about the bill.
The House Committee on Science, Technology & Energy overwhelmingly voted to recommend “Ought To Pass” for HB 569 after considerable public testimony and Committee deliberation.
The bill as recommended provides the New Hampshire Site Evaluation Committee (established in RSA 162-H) with guidance on siting of new electricity transmission lines, guidance which recognizes the value of New Hampshire natural landscapes statewide.
New Section; Criteria
for Approving Transmission Lines for Certificates. Amend
RSA 162-H by inserting after section 2 the following new section:
162-H:2-a Criteria
for Approving Transmission Lines for
Certificates. In determining that a transmission line as
described in RSA 162-H:2, VII(d) and
(e) meets the criteria for
a certificate under this chapter, the committee shall take into consideration the following:
I. Use of existing public rights of way, or, when unavailable, of private
rights of way shall be the preferred, but not required, option for locating all
new electric transmission lines.
II. Burial of electric
transmission lines shall be the preferred, but not required, option for
all elective electric transmission lines with supports over 50 feet.
III. The
committee may presume
that any line not required for system reliability and not proposed
to be substantially buried will
have an
unreasonably adverse effect on
aesthetics. The applicant may,
by a preponderance of the evidence, demonstrate that an above-ground line should be approved due
to particular circumstances, including but
not limited to,
engineering feasibility, adverse environmental impact, substantially
disproportionate cost factors, and
lack of negative impact for the
route involved.
o
The new line should consider using existing
publicly owned rights of way for new transmission facilities
o
Burial should be the preferred option for
elective transmission lines which would otherwise require above ground towers
in excess of 50 feet in height (tree line)
o
Consider the presumption that large new above
ground transmission facilities not needed for reliability of the current
electric grid will have an unreasonably adverse effect on aesthetics
·
If an applicant for a new transmission facility
can demonstrate to the SEC that a preponderance of the evidence warrants that a
new elective transmission line should be built above ground rather than
underground this bill explicitly provides the authority of the SEC to make such
a finding.
·
New Hampshire presently hosts approximately 1400
miles of existing transmission lines. HB
569 will have no impact on these lines.
·
New Hampshire presently hosts approximately
18,000 linear miles of existing distribution lines, the lines that move
electricity to end users. HB 569 will
have no impact on these lines.
·
HB 569 only applies to new transmission lines,
and the burial provision (again not a mandate) only applies to new transmission
lines that are elective, those facilities not needed to serve the reliability
of the electric grid.
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.